Your SPLOST dollars have made numerous transportation improvement projects possible. Because of your support, the following projects were possible:

Location Project
Various Locations Solar Powered School Zone Warning Lights
Cannon Road at White Oak Creek Bridge replacement (Design & Right of Way acquisition)
SR 16 Widening at Sargent Elementary Turn Lanes
SR 16 at East Coweta Middle School Turn Lanes
New Corinth Road at Pine Road Intersection Improvement
Raymond Hill/Fischer/Major/Shaw Intersection reconfiguration & traffic signal
US 29 at Hal Jones/Greentop Intersection improvement
Greentop bridge over CSX Design & Right of Way acquisition
US 29 at Cedar Creek Road Intersection improvement & traffic signal
US 29 at Edgeworth Road Intersection improvement & traffic signal
SR 16 at Macedonia Road Intersection improvement
SR 154 at Lower Fayetteville Road Intersection improvement
Poplar Road at Mary Freeman Road Intersection improvement & traffic signal
Lower Fayetteville at Sullivan Road Intersection improvement & traffic signal
SR 54 at Gordon Road Intersection improvement
Haynie Road Realignment & bridge removal
Nixon Road New surfacing (paved from unpaved)
Glen Winkles Road New surfacing (paved from unpaved)
Reese Road at Keg Creek Bridge replacement
Moore Road at White Oak Tributary Bridge replacement
Lower Fayetteville at Shoal Creek Bridge replacement (Design & Right of Way)
Five Points Intersection Joint Intersection improvement project with City of Newnan
Hood Road Culvert replacement
Club Drive Culvert & Dam replacement
Ishman Ballard Road Culvert replacement
Luther Bailey at Double Branch Bridge replacement
Luther Bailey at Dead Oak Bridge replacement
Cannongate Road Culvert replacement
SR 154 at Hammock Road Intersection improvement & traffic signal (Design & Right of Way)
Poplar Road at SE Bypass Intersection improvement & traffic signal
SE Bypass Extension – Turkey Creek to SR 16 Utilities, design, Right of Way and 20% construction
SR 16 Widening from I 85 to US 29 Design, Right of Way and 20% construction
US 29 at Pine Road Intersection improvement (Design, utilities, Right of Way and 20% construction)
Gordon Road at Moore Road Intersection improvement
Welcome Road at Dixon/Welcome School Intersection improvement